Email evidence supports time extension, defeats general contractor’s delay claim

Posted on June 11, 2015
Posted in Updates

Don’t delete a good email. In United States ex rel. Engineered Services v. T.H.R. Enterprises, a subcontractor defeated a general contractor’s delay claim and won its entire contract balance using email evidence to establish an extended completion date.  The Eastern District of Virginia federal court held that the subcontract completion date was extended to the […]

READ MORE

Notice under Virginia’s Little Miller Act must be received by 90-day deadline

Posted on June 11, 2015
Posted in Updates

Notice that is mailed, but not received, by the 90-day deadline in Virginia’s Little Miller Act is untimely under Virginia law, according to a case of first impression in Norfolk Circuit Court. Subcontractors and suppliers asserting a payment bond claim on a public construction project in Virginia are required by statute to give written notice […]

READ MORE